The Greenway Committee met with Wicklow County Council on Friday 25th September 2026. The following are the minutes from the meeting:
Attendees:
Brian Brennan TD, Malcolm Byrne TD, Cllr Pat Kennedy, Cllr Peter Stapleton, John Bell (engineering consultant, Roughan & O’Donovan [ROD]), Michael Duffy (liaison with landowners, ROD), John Bowes (Wicklow CC engineer), Jed McDermott (Wicklow CC engineer), Pat Canavan & Bill Grantham. Apologies from John Mullen.
John Bell gave a summary of progress to date. The most recent memo on the subject is attached. Some highlights, with contributions from other CoCo and ROD participants:
- Progress through Q3 2026 is up to date, reviewing such features as car parking, access for construction and scoping surveys;
- The topographical survey e-tenders are due on Monday 28th September; a few bids are expected; the internal report on the tenders will take 1-2 weeks to prepare, then the council will approve a successful bid. It is hoped to have the appointment made by the end of October.
- Michael Duffy has started work,
- first of all engaging with landowners. He reported good feedback with only one or two (to date) being less keen on the project
- he will be looking at the possibility of alternative landowners in cases where there are engineering challenges on the existing route
- he’s working in liaison with councillors and committee members in dealing with landowners. Pat Canavan said this had already happened in the initial phase, where Michael is based in the Woodenbridge Hotel.
- Unless all landowners agree — and from experience this is said to be unlikely — the council will proceed with a CPO for all the land. This will follow a process of valuations conducted by independent valuers.
- The deadline for this phase of the project, up to the point of submitting the planning application, is in April 2028. “If things run smoothly” — surveys, assessments, approvals, etc. — there’s potential for the work to be finalised “a little bit sooner”.
- Jed McDermott added that any of the deliverables listed in the memo could be done in parallel with each other to the extent feasible.
- It’s likely that any CPO will be lodged at the same time as the eventual planning application.
- John Bowes emphasised that they were trying to avoid the kinds of problems that blighted the previous Blessington greenway planning application
- As one example, the decision not to route the greenway through Tomnafinnoge Woods, but instead to skirt around it, was taken because of concerns about encroachment on Special Areas of Conservation
- Similarly, attempting to mitigate potential future planning delays, e.g., requests for additional information or decisions to hold oral hearings at the planning stage.
- John Bell said that ROD was beginning to talk to key stakeholders, e.g. the National Parks & Wildlife Service, again to head off future difficulties at an early stage.
- One concern that had been raised was over the status of “hubs” positioned at strategic points along the route. It was emphasised that these hubs would be quite basic, e.g., boards with information about the greenway, and not food or retail outlets that might compete with existing local businesses.
It was agreed that our next meeting should take place at the beginning of January 2027.
The view of the elected representatives and the committee members was that this was a good, business-like meeting with meaningful reports and explanations. We are pleased that the council is meeting its deadlines so far, although we would be happy if any items could be sped up.